                      Project Controls 3.0 (PC-3.0) is designed to build onto
                      the existing developments in project management and
                      project controls to:
                      - Overcome problems in current project management
                         and controls practices, 
                      - Implement a simple, robust system that is effective 
                         for all types of project delivery, and 
                      - Refocus the controls effort on helping management 
                         craft success.
 - Project Controls 3.0 -
                        Contractual Requirements  
                      - PC-3.0 Delays 
                      - Useful Papers & Resources. 
                        Other related sections of the PMKI: 
 - Project Controls 3.0
                        (PC-3.0)  
                      - Work Performance Management
                        (WPM)  
                      - Traditional Project Controls 
                      
- Basic Contract
                        Law
                      - Forensic Analysis 
 Introducing
                      PC-3.0 and the use of Integrated Project Teams (IPTs) for
                      each WU whilst benefiting from a supportive head contract,
                      does not require much change in this level of
                      documentation. The client wants its project delivered on
                      time and to the required quality standards. If PC-3.0 is
                      achieving this everyone will be happy. Generally, a client
                      cannot dictate how a contractor performs its work, and
                      while having client representatives embedded in each IPT
                      is desirable it is not essential.
Introducing
                      PC-3.0 and the use of Integrated Project Teams (IPTs) for
                      each WU whilst benefiting from a supportive head contract,
                      does not require much change in this level of
                      documentation. The client wants its project delivered on
                      time and to the required quality standards. If PC-3.0 is
                      achieving this everyone will be happy. Generally, a client
                      cannot dictate how a contractor performs its work, and
                      while having client representatives embedded in each IPT
                      is desirable it is not essential. 
The project’s subcontracting and procurement activities is where change is needed. The relationship with suppliers and subcontractors needs to be developed to facilitate an adaptive approach focused on success. Various forms of alliance, partnership and gain-share/pain-share contracts are needed.
Blg: Complicated vs Complex – Understanding Complexity. Estimating, planning, and managing a complex project requires a different approach. This post looks at some of the key differences between managing a complicated project and managing a complex project.PC-3.0 has been designed to work in both situations.
 Contrary
                      to modern dogma, you do not need a CPM schedule to assess
                      delay and disruption. Projects using PC-3.0 will
                      inevitably be subject to changes, variations, and
                      disruptions in the same way every other project is, and
                      has been for the last 100+ years. The law relating to
                      contracts, delay, and liquidated damages, was determined
                      in the 19th and early 20th centuries, decades before
                      critical path scheduling (CPM) became commonplace in the
                      1960s.
Contrary
                      to modern dogma, you do not need a CPM schedule to assess
                      delay and disruption. Projects using PC-3.0 will
                      inevitably be subject to changes, variations, and
                      disruptions in the same way every other project is, and
                      has been for the last 100+ years. The law relating to
                      contracts, delay, and liquidated damages, was determined
                      in the 19th and early 20th centuries, decades before
                      critical path scheduling (CPM) became commonplace in the
                      1960s. 
Assessing delay and disruption in projects that are not using CPM requires the same fundamental fact to be demonstrated:
All that changes is the way the delay and its consequences are demonstrated.
The assessment of delays and disruption shifts away from its effect on an arbitrary sequence of activities in a CPM schedule, to understanding the effect of the intervening event on the productivity of the resources working on the project. The best way to make this assessment will depend on the nature of the intervening event. Four adaptations of this basic concept are outlined below:
How these types of delay are calculated are discussed in Assessing Delays in Agile and Distributed Projects.
Click through to see more on assessing delay and disruption.
PP:
                          Assessing Delays in PC-3.0 (Agile &
                          Distributed) Projects. This paper focuses on
                      assessing delay and disruption in PC-3.0 projects where
                      there is no CPM schedule, other agile or adaptive
                      approaches are being used to manage some or all of the
                      work. This paper offers a practical solution to the
                      challenge of assessing delay and disruption in this type
                      of agile and distributed project, where the
                      traditional concept of a ‘critical path’ simply does not
                      exist and the effect of intervening events has to be
                      considered in terms of loss of resource efficiency.
                      Download the PowerPoint: P215 Assessing Delays In Agile &
                          Distributed Projects PPT  
Click through for more on Forensic Schedule Analysis.